Where a nuisance is ordered abated by the Board of Supervisors, the nuisance must be abated within 30 days of the order of the Board of Supervisors, unless the Board of Supervisors grants additional time for the abatement. If after a period of 30 days, or the extended time granted by the Board of Supervisors, the nuisance is not abated, the Planning Department shall enter upon the property in question and abate the nuisance. The Planning Department may request the assistance of the Sierra County Sheriff’s Department to assist in carrying out the abatement order. In abating the nuisance, the Planning Department may utilize its own employees or may contract to have the work done. (Ord. 748, eff. 7/6/89)